Summary
Council gave final approval to zoning rules limiting data centers to accessory uses, capped at 50,000 square feet of floor area in industrial zones and 10,000 elsewhere. A resident pushed for even stricter limits like Munfordville's and raised concerns about water use and buffer distances from homes.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Last discussed Aug 17, 2026.
Impact analysis
Residents worried about large data centers locating near neighborhoods and straining city water get clear, enforceable limits.
Data center developers face tight caps and accessory-use-only restrictions, and some residents say the rules don't go far enough.