Elizabethtown · issues
Civic issues
Topics getting the most attention in Elizabethtown public meetings, ranked by how frequently they come up.
Safe Streets for All Grant Implementation
College Street was funded just before Christmas, but the East Dixie project, announced two years ago, still lacks a signed federal grant agreement — the five-year clock starts only when it's signed.
Arlingwood Court street acceptance
The city is now responsible for maintaining Arnett Place, Mechanical Drive, Camping Circle, and a stretch of Electric Avenue off South Wilson Road, including putting up street and traffic signs.
Traffic calming at Poplar Drive and Meadow Lane
New crosswalks and delineators near Morningside Elementary and T.K. Stone Middle School narrow Poplar Drive to slow speeding traffic where children cross — an inexpensive first step before bigger curb changes.
North Main Street Sidewalk Improvements Phase 3
The city finished sidewalks on Skyline Drive in Glendale Hill and North Main Street, completed a $500,000 federally funded West Railroad Avenue project, and will target Clifford Drive access to Helmwood Heights Elementary next year.
Annual Street Maintenance Contracts
Salt, striping, concrete, milling and limestone bids lock in next year's road maintenance prices, with modest increases of roughly 3-6% over prior years.
Veterans Way construction and speed limit change
The city is spending up to $981,700 to build its first city-funded roundabout at Veterans Way and Towne Drive, in an area flagged for redevelopment. Safety work zones with reduced speed limits will be in place during construction on the fast-moving road.