Safe Streets for All Grant Implementation
College Street was funded just before Christmas, but the East Dixie project, announced two years ago, still lacks a signed federal grant agreement — the five-year clock starts only when it's signed.
Arlingwood Court street acceptance
The city is now responsible for maintaining Arnett Place, Mechanical Drive, Camping Circle, and a stretch of Electric Avenue off South Wilson Road, including putting up street and traffic signs.
Traffic calming at Poplar Drive and Meadow Lane
New crosswalks and delineators near Morningside Elementary and T.K. Stone Middle School narrow Poplar Drive to slow speeding traffic where children cross — an inexpensive first step before bigger curb changes.
North Main Street Sidewalk Improvements Phase 3
The city finished sidewalks on Skyline Drive in Glendale Hill and North Main Street, completed a $500,000 federally funded West Railroad Avenue project, and will target Clifford Drive access to Helmwood Heights Elementary next year.
Annual Street Maintenance Contracts
Salt, striping, concrete, milling and limestone bids lock in next year's road maintenance prices, with modest increases of roughly 3-6% over prior years.
Veterans Way construction and speed limit change
The city is spending up to $981,700 to build its first city-funded roundabout at Veterans Way and Towne Drive, in an area flagged for redevelopment. Safety work zones with reduced speed limits will be in place during construction on the fast-moving road.
Commerce Drive corridor improvement
Commerce Drive is getting curbs and base asphalt, with a water line upgrade and decorative streetlights coming. Sinkholes found at the outdoor music venue have been remediated but are eating into contingency funds that were set aside for other improvements.
Sutton Lane right-of-way closure
Ordinance #04-2026 would close part of Sutton Lane and fold the rest into Commerce Drive. All property owners have given their consent, and a second reading is still to come.
Winter storm response and street clearing
The mayor praised the public works crew for keeping roads passable during the zero-degree snowstorm.
Capital project pipeline — fire station, police station, roads, parks
The fire station should be finished by Jenkins-Essex at the end of the month; the police station hit bad soils but structural steel and roofing are up.